The Work,Measured.

Three engagements. Real crews, real rigs, real numbers, pulled straight from the executive reporting. Anonymized where NDAs require it. We are happy to walk through any of them in detail.

01Rig Case Study02Production Optimization0313-Rig Campaign
[ Case 01 · Drilling Rig Engagement ]

Rig Case Study.

Oil & Gas Sector · Delaware Basin Operations · Key performance indicators, year over year. Same crews. Same equipment. Different leadership culture.

Avg Days Spud to Release
22.5 days
17.5 days
−22%
Non-Productive Time
19.2 hrs
6.5 hrs
−66%
Drilling Efficiency (Code 2)
86 ft/hr
96 ft/hr
+12%
Trip Time Per Well
98.9 hrs
49.0 hrs
−50%

Safety Incidents, Year Over Year

22 → 2 · −91%
22
2024
2
▼ 91% Fewer Incidents
2025

Survey Results

Anonymous · All Levels
0%

Very satisfied with coaching services

0%

Would highly recommend to other teams

0%

Coaches showed high levels of emotional intelligence

0%

Coaching drove measurable improvements

Crews are observed increasing the engagement, and no obvious observations or evidence of complacency.

DSM

I've noticed a huge improvement in communication among the crew.

Driller

ROPE coaches have helped us drive ownership at a faster rate than we've ever seen.

Senior Manager
[ Case 02 · Production Optimization ]

Production, Sustained.

Oil & Gas Production Operation · Coaching & Evaluation Program · Year 1, 7-month snapshot. Launched June, Year 1.

0Structured coaching sessions in seven months
Delivered across Operability, Field Visits, SME Cross-Shares, and LOTO/PSI programs. Launched June, Year 1.
Operability · Launch vs Sustained
96.2%
98%+ sustained
+2.3 pts
LOTO / PSI Incidents · Pre vs Post
28 pre-project → 0 · six months clean
−93%
0%+

Operability sustained
from 96.2% at launch

100

%

LOTO / PSI elimination
28 → 0 sustained

LOTO / PSI Incidents, Eliminated

28 pre-project → 0 sustained · −93%

3.5

Pre-Campaign Avg / Month

0

▼ Down to Zero

Post-Launch · Jul–Dec

SIX MONTHS CLEAN

Pre-Project

28Incidents
JunLaunch
Jul0Clean
Aug0Clean
Sep0Clean
Oct0Clean
Nov0Clean
Dec0Clean

Operability Improvement

Launch: 96.2% · Sustained: 98%+

96.2%

Launch · Jun

98%+

Sustained · Dec
90%92.5%95%97.5%100%

Production operability · scale shown 90–100% · climbed within four months of the June launch and held through December

The Evaluation Framework

ROPE's proprietary platform delivers structured coaching assessments focused on Non-Technical Skills across six core competencies:

01 · Communication

Accuracy · Listening · Feedback

02 · Situational Awareness

Information Gathering · Understanding · Anticipation

03 · Teamwork & Co-operation

Team Building · Supporting Others · Conflict Resolution

04 · Leadership & Assertiveness

Authority · Maintaining Standards · Planning & Prioritizing

05 · Decision Making

Problem Definition · Option Generation · Risk Assessment

06 · Safety Culture Behaviors

Safety Priority · Speaking Up · Compliance

[ Transformation Initiative ]

Legacy-to-Routeless Modernization.

Route-per-Pumper Model → Command Center Operations · Modernization stalled 2+ years. ROPE coaches facilitated implementation of a modernization effort that had been stalled for over two years, moving from a legacy fixed-route model to a dynamic routeless command center approach, achieving full operational adoption during the program.

2yrsSTALLEDFULLY ADOPTEDIN PROGRAM YEAR 1
[ Case 03 · Drilling Rig Campaign ]

Thirteen Rigs.

Executive Performance Overview · Complete rig metrics across a major O&G drilling project. 13 rigs enrolled, 12 assessments complete.

Rigs Through Full Curriculum · 13 Enrolled
12 / 12 active · 100% transition
2.23

Average initial crew score
Non-Technical Skills · scale 0–5

4.20

Average final crew score
+1.97 points · +89% growth

Avg Growth From Baseline
2.23 → 4.20 across 12 rigs
+89%

+1.97

Average score gain, every completed rig improved. 12 of 12 active rigs completed the full curriculum. Highest final score 4.92 (Rig 12). Largest point gain +3.05 (Rig 3).

Performance Progression · All Rigs

Initial 2.23 · Final 4.20

2.23

Initial

4.20

Final
012345

Non-Technical Skills score · scale 0–5 · scored with quantitative ratings and qualitative notes

[ Recordable Injuries · Actively Coached Rigs ]
−95%

Approximate recordable injury reduction on actively coached rigs. First aid incidents dropped ~90% alongside.

+0%Basin-wide drilling performance improvement
Following coaching implementation across the campaign.

What Our Coaches Are Evaluating

01 · Communication

Accuracy · Listening · Feedback

02 · Situational Awareness

Information Gathering · Understanding · Anticipation

03 · Teamwork & Co-operation

Team Building · Supporting Others · Conflict Resolution

04 · Leadership & Assertiveness

Authority · Maintaining Standards · Planning & Prioritizing

05 · Decision Making

Problem Definition · Option Generation · Risk Assessment

06 · Safety Culture Behaviors

Safety Priority · Speaking Up · Compliance